Installation of main pipeline completed

16th February 2016 | John Gransbury

Leed commenced construction of the primary pipelines (39kms) on 28th September 2015 and completed the work by 18th December 2015. Leed’s innovative construction methodology allowed them to achieve an average installation rate of 3.75 km per week. By agreement with the Principal, the trunk main was used by others for 'Early Water' and Practical Completion was deferred until 16/02/2016 when all pipelines could be pressure tested.