Installation of main pipeline completed

26th May, 2016 | Don McQueen

Leed commenced construction of the main pipeline (45kms) on 28th September 2015 and completed the work in on 18th December 2015. Leed’s innovative construction methodology allowed them to achieve an average installation rate of 3.75 km per week. The pipeline has undergone initial testing and will be fully commissioned when integrated into the overall system in mid-2016.